Electrical Generators: Technical Specifications and Power Calculations
Classified in Technology
Written on in
English with a size of 8.85 KB
Electrical Generator Voltage Classifications
Generators are categorized by their voltage output:
- High Voltage: 3kV, 6kV, 10kV, 15kV
- Standard Voltage: 50V–500V
- Special Voltage: 500V–1000V
- Very Low Voltage: <50V (via transformer)
Alternating Current and Engine Types
Generators are classified by phase (biphasic and triphasic) and require an alternator paired with an engine:
- Gasoline: Standard generators
- Diesel: GE (Generator Sets)
- Gas: Large-scale installations
Generator Components and Control Systems
A standard generator assembly includes:
- Safety: Earth connection and 30mA differential protection.
- Control Cabinet:
- Top Box: Ammeter, voltmeter, frequency meter, differential, and emergency stop.
- Lower Cabinet: Terminal board and fast connections (Schuko-type for single and three-phase).
- Mechanical Parts: Alternator, oil heater, motor, radiator, frame, and skid (patin).
Units of Measurement
Standard electrical units include:
- Intensity (I): Amperes (A)
- Voltage (U): Volts (V)
- Power (P): Watts (W)
- Resistance (R): Ohms (Ω)
Sound Levels
- Standard: 80–100 dB
- Protected GE: 60 dB
Operational Cost Comparison
Light Grid vs. Generator Sets (GE):
- Grid: Monthly fixed costs and consumption (kW/h).
- GE: Rental costs, maintenance, and fuel consumption (l/h).
Consumption Formula (l/h) = Power (hp) × Q (Diesel: 0.18 / Petrol: 0.24) × U (0.8)
=
Electrical Standards and Wiring
- Current Types: Single-phase (230V: phase + neutral) and Three-phase (230V or 400V: 2 phases + neutral).
- Color Code:
- Phases: Gray, black, and brown.
- Neutral: Blue.
- Earth: Green-yellow.
- Installation: Aerial (6 meters) or buried (copper or aluminum).
Safety Regulations
- Hose Insulation: 0.6–1kV.
- Differentials: 300mA (triphasic) and 30mA (biphasic).
- Protection Index (IP): Rated for solid object entry, water resistance, and impact resistance.
Documentation Requirements
- <15kW: Installer alert.
- 15–50kW: Technical memory with college visa.
- >50kW: Full project, work plan, and college visa.
- Reactive Power: Required for installations over 15kW.
Power Requirements for Equipment
- Cassette: 3–5kW
- Crane: 13/17/24kW
- Concrete Floor/Standard: 8–100kW / 10–30kW
- Lighting: 500W/floor
- Vibrators: 2/5/8kW
- Wet Cutter: 3/5/7kW
- Trocadora Cutter: 3/5kW
- Welding Group: 5/8/15kW
- Forklifts: 7/10/14kW
- Small Machinery: 5/10/15kW
Power Calculation
Where 0.8 = coefficient of simultaneity and 0.8 = cos φ (for conversion to kVA). Generators are often used as alternative, support, or emergency supplies.