Demolition Methods, Sanitation Networks, and Safety Plans
Classified in Technology
Written on in English with a size of 3.31 KB
Development and Implementation of Demolition
- Dismantling of industrial equipment.
- Demolition or removal of bodies and covered ledges.
- Demolition or removal of the deck.
- Demolition of elements at each plant: interior partition walls, curtain walls, and cargo.
- Demolition of structural elements: forged with beams, reinforced concrete slabs (one-direction, two-directions), beams, brackets, domes.
Types of Demolition
According to Procedure
- Element by element.
- With collapse.
- Mixed or combined.
According to Media
- Manual.
- Mechanical.
- Thermal.
- By explosives.
Design of a Sanitation Network
- If the network is public: Mixed.
- If two networks (wastewater and stormwater): Separator system.
Basic Sanitation Network Requirements
- Dispose of water seal to prevent the passage of air.
- Simple piping layout.
- Appropriate diameter.
- Network accessible for maintenance.
- Have ventilation systems.
- Must not discharge waste other than stormwater or wastewater.
Considerations in Sanitation Network
Tightness and movement of the network.
Types of Evidence in Sanitation Network
- Partial Sealing: Downloading every single device, emptying tests in each section of pipe, manholes, and wells.
- Total Seal: A lump sum or in parts.
All with air, water, or smoke.
Characteristics of Small Evacuation Network
- Length of siphoning boat to the downpipe: <2m.
- Derivations rushing the siphonic boat: <2.5 m with slope 2-4%.
- Individual siphon devices.
- Overflows in toilets, bidets, bathtubs, and sinks.
Qualities Required of a Pool
- Lightweight
- Impervious to wind, rain, or snow
- Cohesion between materials
- Fireproof
- Impact resistance
- Mechanical strength
- Resistance to acid fumes/industrial
Tests to be Done to a Pool
Tightness of risk simulated deck. It's rejected if there is penetration within 48 hours after the test.
Difference Between ESS and PSS
ESS (Estudio de Seguridad y Salud - Health and Safety Study)
- Forms part of the implementation and should be consistent with it.
- Used to build CSS projects or project phases.
- Collects anticipated risks and adequate preventive measures.
- Contains information about safety and health for future action.
- Includes a budget to quantify projected costs, feeding into the general budget of the work as an additional chapter.
PSS (Plan de Seguridad y Salud - Health and Safety Plan)
- Developed by the contractor; estimates discussed in the ESS, and the PSS is produced as the actual implementation of the ESS.
- Must be approved before the start of the work by the Health and Safety Coordinator (HSC).
- Subject to continual changes during the development of the work.
- Carries the same documentation as the ESS planning, complemented by a security force and recommendations.
Types of Hydraulic Seals
- Individual siphon
- Siphon boat
- Chest drain trap